What Happens After You Call
Here's what a typical schedule looks like, from first call to final walkthrough.
01
Site info and quote
3 to 5 business days
Send dimensions, photos, a site plan if available, and a description of the containment goal. Remote estimating from photos and plans is valid for most projects. A site visit isn't always required at the quote stage.
02
Engineering review
1 to 2 weeks
Pole design, cable sizing, foundation specs, and wind-load documentation are finalized. Facilities requiring stamped drawings for permitting receive those as part of this deliverable.
03
Material lead time
2 to 4 weeks
Standard knotless netting and galvanized cable are typically in the shorter range. Custom mesh specifications or specialty pole fabrication push toward the longer end.
04
Installation
3 to 7 days
Most projects install in 3 to 7 days. Larger projects can take 2 weeks or more, and we set that schedule with you up front. We phase work around your operating schedule so you stay open where you can.
05
Tensioning and walkthrough
1 day
Panels are tensioned to the span and load, then we walk the system with you, confirm the scope is complete, and hand over warranty sign-off. One phone number, one warranty.
Times vary with project size. Your schedule is confirmed with your quote.
A note on permitting
The owner or general contractor submits the permit application. We provide stamped engineering drawings to support that application. We don't handle permitting on behalf of owners, but we give you everything you need to move it through.